Use an Acceptance Xbar-R Chart to detect when the out-of-specification percentage might exceed an acceptable level, and monitor the variation using subgroup ranges. Use when you have a subgroup size of 8 or less.

The R chart does not show evidence of unusual variation, so the engineer can interpret the Acceptance Xbar chart. Three subgroup means are above the upper acceptance control limit. These points indicate that the process mean shifted far enough toward the upper specification limit that more than 1% of the process output might exceed the specification limit.
To create an Acceptance Xbar-R chart, choose .