The data you collect for an estimation test can be censored or uncensored. A time-censored test plan or failure-censored test plan often provides precise results while minimizing test costs. For more information, go to Data censoring.
Base your decision about the distribution on process knowledge or an evaluation of the distribution fit. For more information, go to Distribution fit for reliability analysis.
If you select an option with a percentile point, the specifications include the percentile value and the percent. For example, if you expect 15% of units to fail by 100,000 cycles, enter 100000 in Percentile value and 15 in Percent.
Optionally, select that a planning value for a distribution parameter is a fixed, known value. Do not use this option unless there is a strong physical or historical reason.
If you select this option, Minitab assumes that you do not need to estimate this parameter. Therefore, a smaller sample size is required.
The precision of an estimation test plan is based on the width of the confidence interval for the parameter that you are estimating. A wider confidence interval provides a less precise estimate, but requires fewer units to test.