Interpret the key results for an S Chart

Complete the following steps to interpret a S chart. Key output includes the S chart and test results.

Step 1: Determine whether the process variation is in control

The S chart plots the subgroup standard deviations. The center line is the average of all subgroup standard deviations. The control limits on the S chart, which are set at a distance of 3 standard deviations above and below the center line, show the amount of variation that is expected in the subgroup standard deviations.

Red points indicate subgroups that fail at least one of the tests for special causes and are not in control. If the same point fails multiple tests, then the point is labeled with the lowest test number to avoid cluttering the graph. If the chart shows out-of-control points, investigate those points.

Out-of-control points can influence the estimates of process parameters and prevent control limits from truly representing your process. If out-of-control points are due to special causes, then consider omitting these points from the calculations. For more information, go to Specify how to estimate the parameters for S Chart.

In these results, one point is out of control on the S chart. Subgroup 8 is more than 3 standard deviations above the center line. Investigate the process to determine why this subgroup is out of control. When you hold the pointer over a red point, you can see more information about the subgroup.

Step 2: Identify which points failed each test

Investigate any subgroups that fail the tests for special causes. By default, Minitab conducts only Test 1, which detects points that fall outside of the control limits. However, if you conduct additional tests, then points can fail multiple tests. The output shows exactly which points failed each test, as shown here.

S Chart of Faults

S Chart of Faults

Test Results for S Chart of Faults

TEST 1. One point more than 3.00 standard deviations from center line. Test Failed at points: 8
Note

When you use several tests at the same time, the sensitivity of the chart increases. However, the false alarm rate also increases, which can make you react to the test results unnecessarily.

For more information on each of the tests and when to use them, go to Using tests for special causes in control charts.