Expected between/within (B/W) performance for Between/Within Capability Analysis

Find definitions and interpretation guidance for every expected between/within performance measure that is provided with the between/within capability analysis.

PPM < LSL for Expected Between/Within Performance

PPM < LSL for expected between/within performance is the expected number of parts per million that have measurements that are less than the lower specification limit (LSL). Expected between/within performance values are calculated using the between/within standard deviation. PPM < LSL for expected within performance is 1,000,000 times the probability that the measurement of a randomly selected part from the between/within subgroup process distribution is less than LSL.

The probability that a randomly selected part is less than LSL is shown by the shaded region under the between/within normal curve.

Interpretation

Use PPM < LSL for expected between/within performance to estimate the number of nonconforming items, represented in parts per million, that you can expect to be below the lower specification limit based on the variation between/within the subgroups. Between/within performance values indicate the performance that could be achieved if additional sources of systemic process variation, besides the variation between and within subgroups, could be eliminated.

Lower values of PPM < LSL indicate greater process capability, relative to the lower specification limit. Ideally, few or no parts have measurements that are less than the lower specification limit.

PPM > USL for Expected Between/Within Performance

PPM > USL for expected between/within performance is the expected number of parts per million that have measurements that are greater than the upper specification limit (USL). Expected between/within performance values are calculated using the between/within standard deviation. PPM > USL for expected within performance is 1,000,000 times the probability that the measurement of a randomly selected part from the between/within subgroup process distribution is greater than USL.

The probability that a randomly selected part is greater than USL is shown by the shaded region under the between/within normal curve.

Interpretation

Use PPM > USL for expected between/within performance to estimate the number of nonconforming items, represented in parts per million, that you can expect to be above the upper specification limit based on the variation between/within the subgroups. Between/within performance values indicate the performance that could be achieved if additional sources of systemic process variation, besides the variation between and within subgroups, could be eliminated.

Lower values of PPM > USL indicate greater process capability, relative to the upper specification limit. Ideally, few or no parts have measurements that are greater than the upper specification limit.

PPM Total for Expected Between/Within Performance

PPM Total for expected between/within performance is the expected number of parts per million that have measurements that are outside the specification limits. Expected between/within performance values are calculated using the between/within standard deviation. PPM Total for expected between/within performance is 1,000,000 times the probability that the measurement of a randomly selected part from the within-subgroup process distribution is outside the specification limits.

The probability that a randomly selected part is outside the specification limits is shown by the shaded regions under the between/within normal curve.

Interpretation

Use PPM Total for expected between/within performance to estimate the number of nonconforming items, represented in parts per million, that you can expect to be outside the specification limits based on the variation between/within the subgroups. Between/within performance values indicate the performance that could be achieved if additional sources of systemic process variation, besides the variation between and within subgroups, could be eliminated.

Lower values of PPM Total indicate greater process capability. Ideally, few or no parts have measurements that are outside the specification limits.

You can also use PPM to estimate the percentage of conforming and nonconforming parts in your process.
PPM % Nonconforming Parts % Conforming
66807 6.6807% 93.3193%
6210 0.621% 99.379%
233 0.0233% 99.9767%
3.4 0.00034% 99.99966%

% < LSL for Expected Between/Within Performance

% < LSL for expected between/within performance is the expected percentage of parts that have measurements that are less than the lower specification limit (LSL). Expected between/within performance values are calculated using the between/within standard deviation. % < LSL for expected within performance is the probability that the measurement of a randomly selected part from the between/within subgroup process distribution is less than LSL.

The probability that a randomly selected part is less than LSL is shown by the shaded region under the between/within normal curve.

Interpretation

Use % < LSL for expected between/within performance to estimate the percentage of nonconforming items that you can expect to be below the lower specification limit based on the variation between/within the subgroups. Between/within performance values indicate the performance that could be achieved if additional sources of systemic process variation, besides the variation between and within subgroups, could be eliminated.

Lower values of % < LSL indicate greater process capability, relative to the lower specification limit. Ideally, few or no parts have measurements that are less than the lower specification limit.

% > USL for Expected Between/Within Performance

% > USL for expected between/within performance is the expected percentage of parts that have measurements that are greater than the upper specification limit (USL). Expected between/within performance values are calculated using the between/within standard deviation. % > USL for expected within performance is the probability that the measurement of a randomly selected part from the between/within subgroup process distribution is greater than USL

The probability that a randomly selected part is greater than USL is shown by the shaded region under the between/within normal curve.

Interpretation

Use % > USL for expected between/within performance to estimate the percentage of nonconforming items that you can expect to be above the upper specification limit based on the variation between/within the subgroups. Between/within performance values indicate the performance that could be achieved if additional sources of systemic process variation, besides the variation between and within subgroups, could be eliminated.

Lower values of % > USL indicate greater process capability, relative to the upper specification limit. Ideally, few or no parts have measurements that are greater the upper specification limit.

% Total for Expected Between/Within Performance

% Total for expected between/within performance is the expected percentage of parts that have measurements that are outside the specification limits. Expected between/within performance values are calculated using the between/within standard deviation. % Total for expected between/within performance is the probability that the measurement of a randomly selected part from the between/within process distribution is outside the specification limits.

The probability that a randomly selected part is outside the specification limit is shown by the shaded regions under the between/within normal curve.

Interpretation

Use % Total for expected between/within performance to estimate the percentage of nonconforming items, that you can expect to be outside the specification limits based on the variation between/within the subgroups. Between/within performance values indicate the performance that could be achieved if additional sources of systemic process variation, besides the variation between and within subgroups, could be eliminated.

Lower values of % Total indicate greater process capability. Ideally, few or no parts have measurements that are outside the specification limits.

Confidence interval (CI), Lower bound (LB), Upper bound (UB) for expected between/within performance

The confidence interval is a range of likely values for a performance measure. The confidence interval is defined by a lower bound and an upper bound. The bounds are calculated by determining a margin of error for the sample estimate. The lower confidence bound defines a value that the performance measure is likely to be greater than. The upper confidence bound defines a value that the performance measure is likely to be less than.

Note

To display confidence intervals, you must click Options and select Include confidence intervals when you perform the capability analysis. Minitab displays a confidence interval or a confidence bound for the capability indices and the performance measures. Minitab displays separate statistics for the between/within-subgroup variation and the overall variation.

Interpretation

Because samples of data are random, different samples collected from your process are unlikely to yield identical estimates of a performance measure. To calculate the actual value of the performance measure for your process, you would need to analyze data for all the items that the process produces, which is not feasible. Instead, you can use a confidence interval to determine a range of likely values for the performance measure.

At a 95% confidence level, you can be 95% confident that the actual value of the performance measure is contained within the confidence interval. That is, if you collect 100 random samples from your process, you can expect approximately 95 of the samples to produce intervals that contain the actual value of the performance measure.

The confidence interval helps you to assess the practical significance of your sample estimate. When possible, compare the confidence bounds with a benchmark value that is based on process knowledge or industry standards.

For example, a company uses a minimum benchmark value of 0.3% for the % Total out of specification to define a capable process. Using capability analysis, they obtain a % total out of specification estimate of 0.146%, which suggests that the process is capable. To further assess this estimate, they display a 95% upper confidence bound for the % Total out of specification. If the 95% upper confidence bound is less than 0.3%, they can be extremely confident that their process is capable, even when taking into account the variability from random sampling that affects the estimate.