Sets Activity Priority system and properties for future Work Items
The below logic will set Activity 1's Resource Priority to a fixed value of 100.
''Set Work Center Priority Activity 1, Fixed, 100, ""''
The below logic will set Activity 1's Resource Priority to use a Label called lbl_Priority.
''Set Work Center Priority Activity 1, Label, "", lbl_Priority''