This form uses the operation names and cycle times from a process map.
For more information, go to Add and complete a form.
If you have multiple work stations for a single process step, enter the cycle time on the process map as the cycle time divided by the number of stations. For example, suppose that the drilling process step has 4 machines, and the cycle time for one machine is 2 minutes, then the cycle time for that process step is 30 seconds.
To complete a line balance of a proposed cell, you must first create a process map with those steps. You can place shapes without connectors or logic and then enter names and cycle times.