Use the
Quick Changeover (QCO-SMED)
form to compare the internal and external activities of process changeover, or
setup, for both current and improved states.
Use the Shigeo Shingo approach to categorize the setup activities. The
primary goal is to reduce internal setup time, which reduces the amount of
non-productive process time and enables more setups, smaller run batches, and
improved flow.
Internal
Must be done while the process is stopped.
External
Can be done while the process is running, either before or after
performing the setup.
How-to
Enter the project details.
Enter the workstation
details.
Enter the changeover data.
In the
Initial State
and
Improved State
tables, enter each activity and define as
Internal
or
External.
Note
If an element is partly internal and partly external, enter it
twice with the appropriate data. For example, Inspect (internal) = 4 minutes
and Inspect (external) = 8 minutes.